With the first 8 feet of the North side waterproofed, it was time to berm up the fill. Although Dozy is a tough little worker, he is small and his bucket doesn’t cary much material.
On the up side (forgive the pun), Dozy is great for getting into tight spots like here in the NE corner.
Since we had a lot of material to move, we enlisted the help of Tyrell the tracked loader. He made quick work of moving sand up to the house and even did some digging into the hill that will provide some of the additional fill we need to cover our house. (upper right in this photo)
Now we are ready for the waterproofing contractor to come back and continue.